Doing Business with Wright State

Contractor and Designer Resources

On this page:

Dig Permits

  • In what situations should a dig permit be submitted?
    • Tent Installation (when stakes are used)
    • Excavating
    • Boring
    • Post Hole Digging
    • Installing Sign Posts
    • Installing Fencing
    • Any time the ground at WSU is going to be dug, bored, scratched, or otherwise disturbed in anyway.
  • What is the time frame that a Dig Permit should be submitted?

    At least 72 business hours before the work is to take place.

  • Who should submit the Dig Permit?

    Whoever is performing the work.

    • Be it an outside contractor, Physical Plant Employee, Grounds Employee, etc.
    • The Dig Permit can also be submitted by the Project Manager.
       
  • Who is responsible for the Dig Permit being submitted?

    It is the Project Manager’s responsibility along with the contractor/individual performing the work to make sure that a Dig Permit is submitted.

  • Who is responsible for contacting OUPS?

    Whoever is performing the work. Be it an outside contractor, Physical Plant Employee, Grounds Employee, etc.

  • What is the procedure for submitting a Dig Permit?
    1. First the area of work needs to be marked in WHITE paint. This is a requirement of OUPS and WSU
    2. Contact OUPS and record the confirmation number on the Dig Permit
    3. Fill out the remainder of the Dig Permit – all areas of the form MUST be filled out
    4. The Dig Permit must be emailed to digpermit@wright.edu
  • What happens once a Dig Permit is submitted?

    1.      Contractor (Original Submitter) sends scanned completed dig permit to digpermit@wright.edu   (OUPS Number needs to be on permit already)

    OR

    1.   WSU Personnel fills out a dig permit and sends a scanned copy to digpermit@wright.edu  - Physical Plant Customer Service acquires OUPS number

    2.      Physical Plant Customer Service adds a utility map to the permit

    3.      Email the final permit to:

         a.  WSU:  digpermit@wright.edu
         b.  Underground Detectives: Rob Harris robh@ugdet.com
         c.  Original Submitter
     

    4.      CaTS will send a signed permit to digpermit@wright.edu and the Original Submitter

    5.      Underground Detectives will send an onsite locate report to digpermit@wright.edu and the Original Submitter

Dig Permit Form (PDF)

By law, you MUST contact the Ohio Utilities Protection Service at 1-800-362-2764 before digging. You are required to contact them at least 48 hours prior to beginning any digging project, but no more than 10 working days (excluding weekends and legal holidays) before the project. Visit the Ohio Utilities Protection Service website for more information.


Forms and Resources

State Forms

State Forms Policy Update 2/13/13

The Ohio Facilities Construction Commission (OFCC) has created a new Documents webpage for all State forms. In conjunction with this change we have removed all of the State Forms from our webpage so that there is no confusion. You can still download the Wright State Forms below. Please visit the OFCC Forms page for the following document categories:

Forms

  • Concept Development
  • Procurement
  • Design
  • Construction
  • Post-Construction
  • Misc

Standard Requirements

  • Multiple- Prime
  • General Contract
  • CM at Risk
  • Design Build
  • Supplementary
  • Misc

Design Professionals

Contractors


Staff Directory

Javan M. Conley, M.B.A.

Department:
Engineering & Construction
Title:
Construction Administrator
Address:
Medical Sciences 115M, 3640 Colonel Glenn Hwy, Dayton, OH 45435-0001

Chris Gremling, P.E.

Department:
Engineering & Construction
Title:
Senior Project Engineer
Address:
Medical Sciences 115S, 3640 Colonel Glenn Hwy, Dayton, OH 45435-0001

Chris Haring, B.ARCH

Department:
Facilities Planning
Title:
Facilities Planner
Address:
Medical Sciences 115H, 3640 Colonel Glenn Hwy, Dayton, OH 45435-0001

David Kendrick

Department:
Facilities Planning
Title:
Computer Systems Administrator
Address:
115K Medical Sciences Bldg, 3640 Colonel Glenn Hwy, Dayton, OH 45435-0001

Robert A Thompson, B.ARCH

Department:
Facilities Planning
Title:
University Architect
Address:
Medical Sciences 115G, 3640 Colonel Glenn Hwy, Dayton, OH 45435-0001
Phone:
-937-2035

Angie Tipton

Department:
Engineering & Construction
Title:
Budget and Project Accounts Manager Engineering and Construction Department
Address:
Medical Sciences 115N, 3640 Colonel Glenn Hwy, Dayton, OH 45435