Press Box

Classification / Goal: 
Student Experience. To build a permanent Press Box to support Men’s Baseball.
Start Date: 
Sunday, January 1, 2012
Projected End Date: 
Thursday, November 1, 2012
Actual End Date: 
Thursday, November 1, 2012
Stakeholder/Liason: 
Intercollegiate Athletics, Bob Grant
Key Milestone: 
Project Completed - November 2012
Staff: 
Rob Thompson, Architect, Facilities Planning and Management
John Forman, Sr. Project Manager Engineering and Construction
Architect: 
MODA 4
Contractor: 
Synergy
Stage: 
Discovery
Translation
Implementation
Complete